Furniture arrives at the end of the works, but it is decided at the beginning. A hotel that orders its furniture once the painting is finished often discovers it is two months short. Here is the order of the stages and the durations to plan for, starting from the date you want to welcome your first guests.
Start from the opening date
A furnishing schedule is built backwards: opening date, then installation, delivery, manufacturing, mock-up room, design. Each stage has its duration, and manufacturing is the longest. Keep a safety margin for unexpected site issues.
Stage 1: survey and design (2 to 3 weeks)
We measure each room type, list the requirements (bed, headboard, bedside tables, desk, storage, seating, equipment) and design the furniture. This is also the time to set materials, finishes and the budget per room.
Stage 2: mock-up room (1 to 2 weeks)
A complete room is installed and approved with the hotel: dimensions, comfort, finishes, maintenance. Corrections are made at this stage, before the series.
Stage 3: manufacturing (5 to 7 weeks as a rule)
Once the mock-up room is approved, made-to-measure furniture usually takes 5 to 7 weeks to manufacture, longer for complex projects. Meanwhile, the works go on: painting, flooring, electrics.
Stage 4: delivery and installation (a few days to 2 weeks)
The duration depends on the number of rooms and access to the building. On our projects, the 51 rooms of Hôtel des 2 Avenues were installed within one week of delivery. Floors and paintwork must be finished in the rooms concerned.
Don’t forget bedding and equipment
Mattresses, bed bases, minibars, safes, welcome trays, luggage racks: these items must arrive with the furniture, not after it. Ordering them at the same time, from the same supplier, avoids a furnished room that cannot be sold. See our complete hotel room equipment checklist.
Example of a reverse schedule
| Stage | Indicative duration | Before opening |
|---|---|---|
| Survey and design | 2 to 3 weeks | about 14 weeks |
| Mock-up room | 1 to 2 weeks | about 11 weeks |
| Manufacturing | 5 to 7 weeks | about 9 weeks |
| Delivery and installation | a few days to 2 weeks | about 2 weeks |
These durations are indicative: they vary with the size of the hotel and the complexity of the furniture. We confirm them for your project with the quote.