Hotel furnishing: the timeline, from order to opening

How long does it take to furnish a hotel, and in what order? The typical reverse schedule for a hotel furnishing project, to align with your opening or reopening date.

Hôtel des 2 Avenues: hotel room furnished by HCI

Furniture arrives at the end of the works, but it is decided at the beginning. A hotel that orders its furniture once the painting is finished often discovers it is two months short. Here is the order of the stages and the durations to plan for, starting from the date you want to welcome your first guests.

Start from the opening date

A furnishing schedule is built backwards: opening date, then installation, delivery, manufacturing, mock-up room, design. Each stage has its duration, and manufacturing is the longest. Keep a safety margin for unexpected site issues.

Stage 1: survey and design (2 to 3 weeks)

We measure each room type, list the requirements (bed, headboard, bedside tables, desk, storage, seating, equipment) and design the furniture. This is also the time to set materials, finishes and the budget per room.

Stage 2: mock-up room (1 to 2 weeks)

A complete room is installed and approved with the hotel: dimensions, comfort, finishes, maintenance. Corrections are made at this stage, before the series.

Stage 3: manufacturing (5 to 7 weeks as a rule)

Once the mock-up room is approved, made-to-measure furniture usually takes 5 to 7 weeks to manufacture, longer for complex projects. Meanwhile, the works go on: painting, flooring, electrics.

Stage 4: delivery and installation (a few days to 2 weeks)

The duration depends on the number of rooms and access to the building. On our projects, the 51 rooms of Hôtel des 2 Avenues were installed within one week of delivery. Floors and paintwork must be finished in the rooms concerned.

Don’t forget bedding and equipment

Mattresses, bed bases, minibars, safes, welcome trays, luggage racks: these items must arrive with the furniture, not after it. Ordering them at the same time, from the same supplier, avoids a furnished room that cannot be sold. See our complete hotel room equipment checklist.

Example of a reverse schedule

StageIndicative durationBefore opening
Survey and design2 to 3 weeksabout 14 weeks
Mock-up room1 to 2 weeksabout 11 weeks
Manufacturing5 to 7 weeksabout 9 weeks
Delivery and installationa few days to 2 weeksabout 2 weeks

These durations are indicative: they vary with the size of the hotel and the complexity of the furniture. We confirm them for your project with the quote.

Further reading

On our sister site dedicated to custom furniture (in French): manufacturing lead times in detail and planning a hotel renovation.

FAQ

Frequently asked questions

How long does it take to furnish a hotel?

Allow for design and mock-up approval, then 5 to 7 weeks of manufacturing as a rule, and finally delivery and installation, from a few days to one or two weeks depending on the number of rooms.

When should hotel furniture be ordered?

As soon as the room layouts are final, and at the latest three months before opening to keep a margin for design, the mock-up room and manufacturing.

Does the hotel have to close while it is furnished?

Not necessarily. In a renovation, installation can be done floor by floor or in a quiet period to keep some rooms on sale.

Planning an equipment project? Let’s talk.

Send us your room count and requirements, and you will receive a detailed quote within one working day.

WhatsApp