Hotel fit-out: three projects explained, from design to installation

What fitting out a hotel really takes, told through three HCI projects: an 82-room hotel installed in the middle of August, 51 rooms installed in one week, and a mountain chalet.

Grand Hôtel Sénia: room with upholstered fan-shaped headboard and reading lights

A hotel fit-out is judged on site: rooms delivered on the planned date, installed without blocking operations, and built to last. Rather than theory, here are three projects we have carried out, with their constraints and the choices that made them work.

Grand Hôtel Sénia: 82 rooms installed in the middle of August

The challenge: fit out 82 complete rooms in high season without disturbing guests. We manufactured upholstered fan-shaped headboards, wall-hung bedside tables with reading lights, desks and upholstered chairs, open wardrobes and storage, and wall-mounted TV brackets.

The furniture was delivered in 5 weeks and installed in August. “Thank you again for managing the installation in August. We are very pleased with the rooms, especially the headboards,” the management wrote to us.

Hôtel des 2 Avenues: 51 rooms installed in one week

Here, the issue was how long rooms would be out of service. The furniture for the 51 rooms was manufactured in 5 weeks, then everything was installed within one week of delivery: upholstered headboards, bedside tables and reading lights, and bunk beds for the family rooms.

To meet that kind of deadline, the installation schedule is prepared with the management before delivery. “Furnishing the whole property took one week after delivery. Thank you again for keeping to the schedule!” the management summed up.

Chalet Naïga: a made-to-measure mountain fit-out

In Montgenèvre, Chalet Naïga needed a strong identity: solid wood headboards, family rooms and dormitories, a large dining table for the common areas. The 12 rooms and the common areas were delivered in 6 weeks.

In the mountains, site access and weather need to be anticipated in the delivery schedule.

What these three projects have in common

  • An accurate survey of each room type before designing.
  • A mock-up room approved with the hotel before series production.
  • 5 to 7 weeks of manufacturing as a rule, known in advance and aligned with the hotel’s schedule.
  • Planned installation with the management, to keep rooms out of service to a minimum.
  • A single contact for furniture, bedding and equipment.

Further reading

See all our projects and our custom hotel furniture. The step-by-step method is explained on our sister site (in French): hotel fit-out and planning a hotel renovation.

FAQ

Frequently asked questions

What is a hotel fit-out?

It is the design, manufacture and installation of fixed and made-to-measure furniture: headboards, bedside tables, desks, storage, counters, banquettes. It is distinct from decoration and loose equipment, but must be planned with them.

How long does a hotel fit-out take?

Manufacturing usually takes 5 to 7 weeks after mock-up approval. Installation depends on the size of the hotel: one week was enough for the 51 rooms of Hôtel des 2 Avenues.

Can a hotel be fitted out without closing?

Yes, by scheduling installation floor by floor or during a quiet period. At Grand Hôtel Sénia, installation took place in the middle of August.